1. Click the "Gantt View" button
2. You should see the following displayed
3. Every task can have seven inputs
W. O. # - work order number
(optional)
Task - the task itself
(required) (It is good practice to start this with a verb and make it a
complete sentence)
Duration - the estimated
time to complete the task from start to finish (required)
Predecessors - steps
that must be completed before the task is begun (required)
Resources - the resources
required to complete the task (required)
Material Cost - material
cost to complete the task (optional)
Do? - This is a Yes/No
test. (required) If it is decided to do the task, enter 2000
(You can use the Y2000 button).
- VERY IMPORTANT
If it is decided NOT to do the task, enter anything BUT 2000 in the Do?
column and ensure that the "Duration" field = 0h (for 0 hours) AND "Material
Cost" is $0.