Using MSProject98
Viewing the output in MSProject98

1. Click the "Gantt" button.  Adjust the colum widths until you see.

2.  The output consists of three items

Earliest Start  - the earliest start date and time based ONLY on the task durations and predecessors.*
Earliest Finish - the earliest finish date and time (total shutdown duration is shown to the right of "Power and Recovery")
Cost - the total material and labour cost of the shutdown

*This project assumes resources are available as required 7/24/365.